Logistics and maintenance research activities for DONES facility
Metadatos
Afficher la notice complèteMateria
DONES Logistics Maintenance Intralogistics simulation
Date
2023-03-07Referencia bibliográfica
F. Arranz et al. Logistics and maintenance research activities for DONES facility. Fusion Engineering and Design 192 (2023) 113630[https://doi.org/10.1016/j.fusengdes.2023.113630 ]
Patrocinador
European Commission 101052200Résumé
DONES is planned to operate on a continuous basis with only two beam stop periods per year for maintenance.
The planned operational availability is 70 %, which calls for a carefully analyzed preventive maintenance. The
purpose of the research is to propose a realistic and comprehensive logistics and maintenance plan. All the
maintenance activities are included in a Maintenance Matrix based on the Plant Breakdown Structure of the
project. This is the basis for the creation of a maintenance plan that will lead to a Work Schedule. Special mention
within this matrix will be given to those Maintenance operations that must be included in order to comply with
regulation. The need of replacement of components impose some requirements on the dimensions of architec tural features of the main building such as doors, airlocks, corridors and shipping bays. To enable these re placements, the flow of materials has been developed and analyzed by an intralogistics simulation with
AnyLogic. The results of this simulation lead to modifications on either the building or the components such that
the replacements are feasible. The periodic replacement of an activated component has been analyzed using
FMEA methodology resulting in proposals for the plant equipment designers as well as the remote handling
equipment designers. Virtual reality simulations are used for a staged approach to the maintenance operation.
The simulation of the HEBT scraper helped to define in detail each step or the maintenance operation. This tool
has proven to be very useful to prompt changes in both the plant equipment design and the remote handling
equipment. Also, the procedure of the operation itself can be refined and optimized. The conclusion of the
research activities is the contribution to the definition of the building, plant equipment and achievement of the
target availability.