TY - GEN AU - Para-González, Lorena AU - Mascaraque-Ramírez, Carlos AU - Madrid García, Ana Esther PY - 2018 UR - https://hdl.handle.net/10481/94634 AB - The naval sector of new construction is characterised by high cost programmes and a low degree of definition in the stages of tendering. With these requirements, an initial, highlycompetitive budget should be developed with acceptable risk. For this... LA - eng PB - University of Zagreb KW - Budget Contingency Reserve KW - Monte Carlo simulation KW - Project Management KW - Shipbuilding project KW - Uncertainty TI - Obtaining the budget contingency reserve through the monte carlo method: Study of a ferry construction project DO - 10.21278/BROD69305 ER -