dc.contributor.authorSobieraj, Janusz
dc.contributor.authorMetelski, Dominik Igor
dc.date.accessioned2022-03-18T08:43:16Z
dc.date.available2022-03-18T08:43:16Z
dc.date.issued2022-01-20
dc.identifier.citationSobieraj, J.; Metelski, D. Project Risk in the Context of Construction Schedules—Combined Monte Carlo Simulation and Time at Risk (TaR) Approach: Insights from the Fort Bema Housing Estate Complex. Appl. Sci. 2022, 12, 1044. [https://doi.org/10.3390/app12031044]es_ES
dc.identifier.urihttp://hdl.handle.net/10481/73539
dc.description.abstractIn this article, we present our own construction process model consisting of 16 stages and eight phases, which is particularly applicable to large investment projects. In the context of each project phase, we examine how the appropriate way of scheduling construction processes affects the problem of the risk of prolonging individual phases and the whole project, as well as of not meeting deadlines (which is one of the main problems faced by management practitioners in the construction industry). There are many methods for assessing risk in this context, but they tend to be overly complex and rarely used by construction practitioners. On the other hand, the risks associated with potential schedule delays can be considered holistically. One tool that can serve this purpose is the combined Monte Carlo simulation and Time-at-Risk (TaR) approach, which originates from the world of finance. We show how the implementation of the process model (individual phases) and the whole project can be considered in the context of the covariance matrix between all its phases and how changes in the arrangement of these phases can affect the risk of time extension of the whole project. Our study is based on simulation data for a large development project (Fort Bema/Parkowo-Le´sne housing estate complex) in Bemowo, a district ofWarsaw, carried out between 1999 and 2012. The entire investment project involved the construction of almost 120,000 m2 of floor space.es_ES
dc.language.isoenges_ES
dc.publisherMDPIes_ES
dc.rightsAtribución 3.0 España*
dc.rights.urihttp://creativecommons.org/licenses/by/3.0/es/*
dc.subjectTime scheduleses_ES
dc.subjectProject riskes_ES
dc.subjectConstruction project managementes_ES
dc.subjectTime-at-Risk (TaR)es_ES
dc.subjectInvestment-construction process modeles_ES
dc.subjectMonte Carlo simulationes_ES
dc.titleProject Risk in the Context of Construction Schedules—Combined Monte Carlo Simulation and Time at Risk (TaR) Approach: Insights from the Fort Bema Housing Estate Complexes_ES
dc.typejournal articlees_ES
dc.rights.accessRightsopen accesses_ES
dc.identifier.doi10.3390/app12031044
dc.type.hasVersionVoRes_ES


Ficheros en el ítem

[PDF]

Este ítem aparece en la(s) siguiente(s) colección(ones)

Mostrar el registro sencillo del ítem

Atribución 3.0 España
Excepto si se señala otra cosa, la licencia del ítem se describe como Atribución 3.0 España